18 St. Paul school projects, $179 million over estimates

$
0
0

The costs of building renovations throughout the St. Paul school district are coming in far higher than expected in 2016.

For 18 high-priority projects, the Pioneer Press has compared estimates from the district’s 2016 Facilities Master Plan to recently updated figures, which are a combination of actual costs and revised estimates.

That review found those 18 buildings are expected to cost $179 million more than the $292 million estimate from three years earlier.

RELATED: St. Paul schools construction costs skyrocket. What’s the impact and what are the causes?

The schools and the costs:

HUMBOLDT HIGH

Humboldt High School, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $48 million, according to a fall 2018 estimate.
  • Earlier projection: $26.8 million estimated cost in 2016.
  • Progress: Construction began in 2017 and should be done in August 2020.

HIGHLAND PARK COMPLEX

Highland Park Complex, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $34.5 million, according to a fall 2018 funding request.
  • Earlier projection: $16.5 million estimated cost in 2016.
  • Progress: Construction was delayed four years to 2022 when numerous projects ended up costing far more than expected.

OBAMA ELEMENTARY

Obama Elementary, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $36.4 million, according to a fall 2018 funding request.
  • Earlier projection: $19.1 million estimated cost in 2016.
  • Progress: Construction was delayed three years to 2023 when numerous projects ended up costing far more than expected.

AMERICAN INDIAN MAGNET

American Indian Magnet, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $38.5 million, according to a fall 2018 funding request.
  • Earlier projection: $23.1 million estimated cost in 2016.
  • Progress: Construction was delayed one year to 2020 when numerous projects ended up costing far more than expected.

COMO PARK SENIOR HIGH

Como Park Senior High, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $46.8 million, according to a fall 2018 estimate.
  • Earlier projection: $32.4 million estimated cost in 2016.
  • Progress: Construction began in 2017 and should be done in late 2019.

RAMSEY MIDDLE SCHOOL

Ramsey Middle School, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $23.5 million, according to a fall 2018 funding request.
  • Earlier projection: $11.4 million estimated cost in 2016.
  • Progress: Construction was delayed one year to 2021 when numerous projects ended up costing far more than expected.

BRUCE VENTO ELEMENTARY

Bruce Vento Elementary, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $25 million, according to a spring 2018 estimate.
  • Earlier projection: $13.6 million estimated cost in 2016.
  • Progress: Construction is planned for 2020.

FARNSWORTH AEROSPACE LOWER CAMPUS

Farnsworth Aerospace Lower Campus, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $26.1 million, according to a fall 2018 funding request.
  • Earlier projection: $17.1 million estimated cost in 2016.
  • Progress: Construction was delayed two years to 2022 when numerous projects ended up costing far more than expected.

FROST LAKE ELEMENTARY

Frost Lake Elementary, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $25.5 million, according to a spring 2018 estimate.
  • Earlier projection: $16.9 million estimated cost in 2016.
  • Progress: Construction is planned for 2020.

LINWOOD MONROE ARTS-PLUS LOWER CAMPUS

Linwood Monroe Arts-Plus Lower Campus, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations were expected to cost $23.5 million as of fall 2018.
  • Earlier projection: $15 million estimated cost in 2016.
  • Progress: Construction was completed in fall 2018.

HORACE MANN ELEMENTARY

Horace Mann Elementary, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will have cost around $18.9 million, according to a fall 2018 funding request.
  • Earlier projection: $11.4 million estimated cost in 2016.
  • Progress: Construction was completed in 2018.

LINWOOD MONROE UPPER CAMPUS

Linwood Monroe Upper Campus, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will have cost around $22.2 million, according to a fall 2018 funding request.
  • Earlier projection: $15.4 million estimated cost in 2016.
  • Progress: Construction was completed in 2018.

DISTRICT SERVICE CENTER

District service center, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $15 million, according to a fall 2018 funding request.
  • Earlier projection: $8.6 million estimated cost in 2016.
  • Progress: Construction was delayed three years to 2020 when numerous projects ended up costing far more than expected.

ADAMS SPANISH IMMERSION

Adams Spanish Immersion, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations were expected to cost $24 million as of fall 2018.
  • Earlier projection: $17.7 million estimated cost in 2016.
  • Progress: The project was largely finished by late 2018.

ST. ANTHONY PARK ELEMENTARY

St. Anthony Park Elementary, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will have cost around $19.9 million, according to a spring 2018 estimate.
  • Earlier projection: $14 million estimated cost in 2016.
  • Progress: Construction was completed in 2018.

CHEROKEE HEIGHTS ELEMENTARY

Cherokee Heights Elementary, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $17 million, according to a fall 2018 funding request.
  • Earlier projection: $11.7 million estimated cost in 2016.
  • Progress: Construction was delayed one year to 2021 when numerous projects ended up costing far more than expected.


HIGHLAND PARK ELEMENTARY

Highland Park Elementary, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will have cost around $20.6 million, according to a spring 2018 estimate.
  • Earlier projection: $17.8 million estimated cost in 2016.
  • Progress: Construction was completed in 2018.

PHALEN LAKE HMONG STUDIES

Phalen Lake Hmong Studies, pictured April 3, 2019. (Josh Verges / Pioneer Press)
  • Price tag: Renovations will cost around $5.5 million, according to a fall 2018 funding request.
  • Earlier projection: $3.7 million estimated cost in 2016.
  • Progress: Construction was delayed one year to 2020 when numerous projects ended up costing far more than expected.